Menard Electric Line Extension Policy
Line Extension Fees
|
| June 1, 2010 |
| Item |
Member
Cost |
| Single Phase Basic Construction Charge |
$150 |
| Three Phase Basic Construction Charge |
$300 |
| Three Phase Line Tap Fee (Where Applicable) |
$2,500 |
| |
|
|
| Primary |
|
Member
(Cost / Ft.) |
| Single Phase Overhead Primary |
First 300 ft. |
$0.00 |
| |
From 300 to 1,300 ft. |
$1.25 |
| |
All over 1,300 ft. |
$2.50 |
| Single Phase Underground Primary |
First 300 ft. |
$3.00 |
| (Trenching
Service Charge $100) |
From 300 to 1,300 ft. |
$4.25 |
| |
All over 1,300 ft. |
$5.50 |
| Three Phase Overhead Primary |
First 300 ft. |
$0.00 |
| |
From 300 to 1,300 ft. |
$2.50 |
| |
All over 1,300 ft. |
$5.00 |
| Three Phase Underground Primary |
First 300 ft. |
$5.00 |
| (Trenching
Service Charge $100) |
From 300 to 1,300 ft. |
$7.50 |
| |
All over 1,300 ft. |
$10.00 |
| Single Phase to Three Phase Overhead Conversion |
First 300 ft. |
$0.00 |
| |
From 300 to 1,300 ft. |
$1.50 |
| |
All over 1,300 ft. |
$3.00 |
| |
|
|
| Secondary |
|
Member
(Cost / ft.) |
| Single Phase Overhead Secondary |
First 100 ft. |
$0.50 |
| |
All over 100 ft |
$1.00 |
| Single Phase Underground Secondary |
First 100 ft. |
$3.50 |
| (Trenching
Service Charge $100) |
All over 100 ft. |
$4.00 |
| Three Phase Overhead Secondary |
First 100 ft. |
$1.00 |
| |
All over 100 ft. |
$1.75 |
| Three Phase Underground Secondary |
|
Installed By Member |
| Underground Directional Boring |
|
$8.00 |
|
(Boring Service Charge $250) |
|
|
| Transformers & Convertors |
|
Member Cost |
| Single Phase Overhead Transformer |
50% Cost of Overhead Unit |
$450 |
| Single Phase Pad-Mount Transformer |
Difference + OH Cost |
$900 |
| Three Phase Overhead Transformer |
50% Cost of Overhead Bank |
$1,300 |
| Three Phase Pad-Mount Transformer |
|
Price on Request |
| Phase Converter (Subject to Engineering Approval) |
|
Price on Request |
|