SECTION IV - Operating Rules for Consumers and/or Members
INTERCONNECTION AND PARALLEL OPERATION OF
DISTRIBUTED GENERATION
Download
Attachments & Exhibits (including application forms) For This Policy
I.
OBJECTIVE
To establish safety, reliability and economic
standards for interconnection and parallel operation of member-owned
distributed generation facilities designed primarily to offset the
member's electrical requirements while honoring the Cooperative's
obligation to provide electricity to all members on a cooperative
basis, and which may encourage the development of member-owned
on-site electric generation facilities using renewable fuel sources.
II.
DEFINITIONS
Distributed generation is defined as any
generation built within close proximity to the generating member's
load regardless of generation capacity or energy source of such
generation and includes but is not limited to:
A.
small scale environmentally friendly
generators such as photovoltaics (PV), fuel cells, small wind
turbines;
B.
microturbines or reciprocating
engines fueled by renewable fuels such as landfill gas or methane
gas from digesters;
C.
any qualifying facility (QF) under
the Public Utility Regulatory Policies Act of 1978 (PURPA);
D.
any on-site generation interconnected
with distribution facilities;
E.
commercial emergency and standby
diesel generators installed, for example, in hospitals, hotels and
farms;
F.
residential standby generators;
G.
generators installed by a utility at
a substation for voltage support or other reliability purposes.
IEEE STANDARD 1547 - The Institute of Electrical
and Electronic Engineers, INC.
(IEEE) Standard 1547 (2003) "Standard for Interconnecting
Distributed Resources with Electric Power Systems", as amended and
supplemented, at the time the interconnection request is submitted.
IEEE STANDARD 1547.1 - The IEEE Standard
1547.1 (2005) "Conformance Test Procedures for Equipment
Interconnecting Distributed Resources with Electric Power Systems",
as amended and supplemented, at the time the interconnection request
is submitted.
NAMEPLATE
CAPACITY - The maximum rated output of a
generator, prime mover, or other electric power production equipment
under specific conditions designated by the manufacturer and is
usually indicated on a nameplate physically attached to the power
production equipment.
SMALL GENERATOR FACILITY
- The equipment used by an
interconnection customer to generate, or store electricity that
operates in parallel with the electric distribution system with a
nameplate capacity of 10 kW or less.
A small generator facility typically includes an electric
generator, prime mover, and the interconnection equipment required
to safely interconnect with the electric distribution system or
local electric power system.
These facilities have been approved by a nationally
recognized testing laboratory or must have been approved by the
Cooperative under a study process and qualify for expedited review.
UL STANDARD 1741 - Underwriters
Laboratories' standard titled "Inverters, Converters, and
Controllers for Use in Independent Power Systems", November 7, 2005
edition, as amended and supplemented.
WITNESS TEST - For lab certified or field
approved equipment, verification (either by an on-site observation
or review of documents) by the Cooperative that the interconnection
installation evaluation required by IEEE Standard 1547 Section 5.3
and the commissioning test required by IEEE Standard 1547 Section
5.4 have been adequately performed.
For interconnection equipment that has not been lab certified
or field approved, the witness test shall also include the
verification by the Cooperative of the on-site design tests as
required by IEEE Standard 1547 Section 5.1 and verification by the
Cooperative of production tests required by IEEE Standard 1547
Section 5.2. All tests
verified by the Cooperative are to be performed in accordance with
the test procedures specified by IEEE Standard 1547.1.
III.
APPLICABILITY
This interconnection policy applies to
Cooperative members proposing to install and interconnect generator
facilities that:
A.
Have a nameplate capacity equal to or
less than 1 MW;
B.
Are not subject to the
interconnection requirements of MISO, and
C.
Are designed to operate in parallel
with the electric distribution system.
IV.
INTERCONNECTION REQUESTS
A.
Members seeking to interconnect a
generator facility shall submit an interconnection request using the
form attached hereto as Attachment A.
The request may be eligible for expedited interconnection
review if the request is for a small generator facility using lab
certified or field approved interconnection equipment, and where the
aggregate distributed generation on the affected distribution
circuit is less than 10% of the minimum load on the circuit.
B.
Interconnection equipment shall be
deemed to be lab certified if it is evaluated by a nationally
recognized testing laboratory (NRTL) and found to be in compliance
with IEEE 1547 Standard for Interconnecting Distributed Resources
with Electric Power Systems (including use of IEEE 1547.1 testing
protocols to establish conformity), UL 1741 Inverters, Converters,
and Controllers for Use in Independent Power Systems and NFPA 70
National Electrical Code.
C.
Interconnection equipment shall be
deemed to be field approved if within the previous 36 months of the
date of the interconnection request, it has been previously approved
for use with the proposed small generator facility in a materially
identical system application, and the prior approval process
included a successful witness test.
D.
The member must submit to the
Cooperative plans of the proposed installation and must obtain
approval for the installation.
This approval process will include a review by the
Cooperative of the effect of the proposed generation on the
Cooperative's distribution system, including both the protective
scheme of the proposed generator and that of the Cooperative. The member requesting
interconnection shall pay the cost of this review. No installation will be
permitted that reduces reliability to other members or causes
voltage conditions on the system to be outside of the limits of ANSI
C84.1 Range A. No
installation will be permitted that is expected to produce
objectionable harmonics on the system. Any mitigation required to
resolve harmonic problems created by a member-owned generator will
be completed and paid for by the member.
E.
For generating facilities with
nameplate ratings greater than 10 kW up to and including 1 MW, the
Cooperative shall supply, to the extent practicable and as
determined to be in the best interest of the Cooperative, the
procedures contained in the Small Generator Interconnection
Procedures (SGIP) for generating facilities no larger than 20 MW as
developed by the Federal Energy Regulatory Commission (FERC) and the
Illinois Commerce Commission regulations governing interconnection
standards.
V.
EXPEDITED REVIEW
A.
The Cooperative shall review the
application and evaluate the potential for adverse system impacts. Any costs of construction of
facilities on the Cooperative's system to accommodate the small
generator facility shall be paid by the member.
B.
The Cooperative shall, within 20
business days after receipt of the interconnection request, inform
the applicant that the interconnection request is complete or
incomplete and if so, what materials are missing.
C.
The Cooperative shall, within 30
business days after the end of the 20 business days noted in B,
verify that the small generator facility equipment can be
interconnected safely and reliably.
D.
Unless the Cooperative determines and
demonstrates that a small generator facility cannot be
interconnected safely or reliably to its system and provides a
letter to the applicant explaining its reasons for denying an
interconnection request, the Cooperative shall approve the
interconnection request subject to the following conditions:
1.
The small generator facility has been
approved by local or municipal electric code officials with
jurisdiction over the interconnections; and
2.
A certificate of completion has been
returned to the Cooperative.
Completion of local inspections may be designated on
inspection forms used by local inspecting authorities; and
3.
The witness test has been
successfully completed or waived; and
4.
The applicant has signed a standard
small generator interconnection agreement and provided proof of
insurance or otherwise complied with the terms of the agreement. When an applicant does not
sign the agreement within 30 business days after receipt from the
Cooperative, the interconnection request may be deemed withdrawn
unless the applicant requests to have the deadline extended. The request for extension
shall not be unreasonable denied by the Cooperative.
E.
When a small generator facility is
not approved under this expedited review, the applicant may submit a
new interconnection request for consideration under the procedures
for review of larger capacity generator facilities with a nameplate
capacity greater than 10 kW and less than 1 MW.
VI.
INSURANCE REQUIREMENTS AND INDEMNIFICATION
A.
Throughout the term of this
agreement, the Member shall carry a liability insurance policy
issued by a licensed insurance carrier with an A. M. Best rating of B+ or better
that provides protection against claims for damages resulting from
(i) bodily injury, including wrongful death; and (ii) property
damage arising out of the member's ownership and/or operation of the
distributed generation facility under this agreement. The limits of such policy
shall be at least $1,000,000 per occurrence for those members with
generation facilities.
The member shall provide a certificate of insurance containing a
minimum 30 day notice of cancellation to the Cooperative prior to
connection of the member's facility to the Cooperative's system.
B.
In the event the member chooses to
self-insure, the member shall provide proof of financial
responsibility satisfactory to the Cooperative and shall indemnify
the Cooperative, its officers, agents, and employees against all
loss, damage, expense and liability to any persons, including
members, for injury to or death of persons or injury to property,
including but not limited to consequential damages, interest,
punitive damages, member's fees and court costs, proximately caused
by the indemnifying party's construction, ownership,
interconnection, operation, or maintenance of, or by failure of, any
of such party's works or facilities used in connection with the
operation of the generating facility.
VII.
MISCELLANEOUS REQUIREMENTS
A.
The Cooperative shall be reimbursed
for all costs of interconnection, including all carrying costs,
incurred by the Cooperative in connecting the member generation
facility to the distribution system.
Those costs for a small generating facility shall not exceed
$500 unless the facility fails initial testing and additional review
is necessary.
B.
The Cooperative shall have free
access to the member's generation facility and interconnection
equipment at all times to monitor operation of the member's
equipment, Cooperative-supplied service equipment connected to such
system, or to disconnect if the facility is not in compliance with
the requirements of IEEE 1547 and the non-compliance adversely
affects the safety or reliability of the electric system. The Cooperative shall provide
reasonable notice to the member prior to disconnection of the
facility if possible.
C.
The Cooperative shall have the right
to inspect and approve all plans for parallel generation systems and
the interconnection systems prior to initial operation or subsequent
operation following modifications.
D.
The member shall make any necessary
changes or adjustments to the additional facilities being operated
in parallel to eliminate interference on the Cooperative's
distribution system.
E.
The member shall not energize the
Cooperative's system during any period of utility service
interruption. The
member's equipment must contain a disconnect device to which the
Cooperative has access and which the Cooperative can lock in an open
position to disconnect, for safety reasons, the member's electric
generating facility from the Cooperative's electric delivery system.
F.
Electric generation facilities may be
disconnected by the Cooperative from its system whenever, in the
sole opinion of the Cooperative, such action is required by an
emergency, for reasons of safety or due to interference with service
to other members. The
facility shall also be subject to the Cooperative's requirements for
maintaining voltage standards of output and the production of
reactive power.
G.
Phasing, frequency and voltage of the
member's interconnected generation shall be compatible with that
provided by the Cooperative.
H.
The members shall pay the cost of
interconnection including initial and future transmission,
distribution, metering, service and other facilities costs necessary
to permit interconnected operations with the Cooperative.
I.
Any auxiliary or reserve power
service required by the member must be arranged in accordance with
the terms of the Cooperative's applicable policies/rates as modified
from time to time.
J.
In the event of a dispute, either
Party shall provide the other Party with a written Notice of Dispute
describing in detail the nature of the dispute. If the dispute has not been
resolved within thirty (30) business days after receipt of the
Notice, either Party may request assistance from the Menard Electric
Cooperative Board of Directors in resolving the dispute. If the attempted dispute
resolution fails, then either Party may exercise whatever rights and
remedies it may have in equity or law consistent with the terms of
this policy.
APPROVED BY BOARD OF DIRECTORS 3-25-08